A and B can do a piece of work in 35 and 40 days respectively. They started the work together but A left the work after some time and B finished the remaining work in 23 days. Find out after how many days A left the work (approx.)?
Answer
Correct Answer : a ) 8
Explanation :Basic Method:
Time Taken by A to complete the work = 35 days
Work done by A in 1 day = \(1 \over 35\) units
Time Taken by B to complete the work = 40 days
Work done by B in 1 day = \(1\over40\) units
Work done by A and B together in 1 day (Efficiency of A and B together):
⇒\(1 \over 35\)+ \(1\over40\)= \(15\over280\)
B work alone for 23 days
Work done by B in 23 days= \(23 \over 40\) units
Assume the complete work being done is 1
Work done by A and B together= 1- \(23 \over 40\)=\(17 \over 40\)
Time taken to complete the work= \(Total work \over Efficiency\)
Time taken by A and B to do 17/40 units of work = \({{17\over40}\over{15\over280}}={{17*280}\over{40*15}}\)
⇒ 7.9333 days (Approx. ≈8 days)
Therefore, A left the work after 8 days.
Alternative Method:
Time Taken by A to complete the work = 35 days
Time Taken by B to complete the work = 40 days
Let’s assume total work done by A and B = LCM (35, 40) = 280
Work done by A in 1 day= \(280 \over 35\)=8 units
Time Taken by B to complete the work = 40 days
Work done by B in 1 day= \(280\over 40\)=7 units
B work alone for 23 days
Work done by B alone = 23*7 = 161
Remaining work done by A and B together = 280-161 = 119
Work done by A and B together in 1 day = 8 + 7 = 15 units
Time taken by A and B to do the remaining work:
⇒\(119 \over 15\)=7.93333.. (Approx. ≈8)
Therefore, A left the work after 8 days.
Hence, (a) is the correct answer.
Comments